Design and construction of the water supply system for the villages of Gurjaani Municipality - Jimithi and Nanyani

The project envisages the design and maintenance of drinking water supply for two villages, Jimithi and Nanyani, in total 30,900 long/m plastic pipes of different diameters are planned. As a result, up to 800 families will be supplied with water.

The project envisages the arrangement of 4 design wells of 200 meters, the construction of a 300 m3 reinforced concrete reservoir and the repair work of the existing 500 m3 reservoir.

For the current period, 27,000 l/m of drinking water pipes have been installed, a design reservoir of 300 m3 has been built, and the works of the technological part of the said construction are in progress.  Also, 3 wells have been drilled.